Day 2: Friday, Nov 11th.
Got the whole family up early for when the scaffolders arrived. (Not too much of a stretch for me since I’m up early, but the kids are not such an easy proposition).
No scaffolders by 0830. Various phonecalls later. They’ll be there at 10, 10:30, an hour, a while etc.
The roofers showed up on time, but couldn’t do anything. So they headed down the local café for a full English.
12:30 the scaffolders show up. The roofers in the mean time have gone back home – they won’t be able to start in time to complete the work today.
2 hours or so we have scaffolding. Finally some signs of progress.
An hour or so later the equipment arrives from the solar wholesaler. It’s a good job I’m there – someone has to help with the unloading and sign for the equipment.
The panels are not quite as expected, instead of Yingli 240W panel I’ve got Q-cell 245W panels. Some research required to see if that’s ok.
Scaffolding in place:
Panels in the garage:
Box of bits (but no inverter):